MECHANICS LIEN RECORDING IN LINCOLN COUNTY, WASHINGTON

The Lincoln County Auditor’s Office in Davenport serves this wheat-farming region of eastern Washington, recording mechanics liens for jobs across the county.

Lincoln County Mechanics Lien Deadlines

  • Preliminary Notice: 60 days from first furnishing labor/materials, if no direct owner contract.
  • Filing Deadline: 90 days from last day of work (RCW 60.04).
  • Foreclosure Deadline: 8 months from recording.

Lincoln County Auditor’s Office

Why File Through CNS

  • Ensure you’re filing in the right Lincoln County for the state where the property sits
  • Accurate legal descriptions

FAQ

How long do I have to file in Lincoln County, WA?

90 days from your last day of work on the project.

What happens if I don’t send a preliminary notice?

If you weren’t under direct contract with the owner and skip the 60-day notice, your lien claim can be limited or invalidated. 