MECHANICS LIEN RECORDING IN LINCOLN COUNTY, NEVADA
The Lincoln County Recorder’s Office in Pioche, a former silver-mining town in rural eastern Nevada, records mechanics liens for the county.
Lincoln County Mechanics Lien Deadlines
- Notice of Right to Lien: Must be sent within 31 days of first providing labor or materials (ORS 87.021).
- Notice of Intent to Lien: 15 days before recording on residential jobs.
- Filing Deadline: 90 days from last work/materials/completion, or 40 days if a Notice of Completion is recorded (NRS 108.226).
- Foreclosure Deadline: 6 months from recording.
Lincoln County Recorder’s Office
- 181 N Main St, Pioche, NV 89043
- lincolncountynv.org/ra/
Why File Through CNS
- We verify that the correct Lincoln County applies to your project
- We can monitor for a recorded Notice of Completion that shortens your filing window (additional service)
- We offer full claim preparation and recording
FAQ
How long do I have to file a mechanics lien in Lincoln County, NV?
90 days, or 40 days if the owner records a Notice of Completion.
What’s a Notice of Intent to Lien?
A required 15-day notice before recording on residential property in Nevada.