MECHANICS LIEN RECORDING IN JEFFERSON COUNTY, WASHINGTON
The Jefferson County Auditor’s Office in Port Townsend, a historic seaport on the Olympic Peninsula, records mechanics liens for construction projects throughout the county.
Jefferson County Mechanics Lien Deadlines
- Preliminary Notice: 60 days from first work if no direct contract with the owner.
- Filing Deadline: 90 days from last day of work (RCW 60.04.091).
- Foreclosure Deadline: 8 months from recording.
Jefferson County Auditor’s Office
- 1820 Jefferson St, Port Townsend, WA 98368
- co.jefferson.wa.us/auditor/recording/Recording.asp
Why File Through CNS
- Confirm you’re filing against the correct Jefferson County (WA vs. OR)
- Claim preparation that meets RCW’s exact statutory form
FAQ
How long do I have to file a mechanics lien in Jefferson County, WA?
90 days from your last day supplying labor, materials or equipment.
Do I need to serve the owner after recording?
Yes, Washington law requires you to serve a copy of the recorded lien on the owner within 14 days, or you risk losing the right to recover attorney’s fees.