MECHANICS LIEN (CONSTRUCTION LIEN) RECORDING IN JEFFERSON COUNTY, OREGON
The Jefferson County Clerk in Madras records construction liens for the high-desert farming region of central Oregon. Here’s the timeline Oregon law requires for getting paid.
Jefferson County Construction Lien Deadlines
- Notice of Right to Lien: 8 business days from first furnishing on residential jobs, with no direct owner contract.
- Filing Deadline: 75 days from last furnishing or completion, whichever is earlier (ORS 87.035).
- Foreclosure Deadline: 120 days from filing.
Jefferson County Clerk’s Office
- 66 SE D St Suite C, Madras, OR 97741
- co.jefferson.or.us/CountyClerk/tabid/1382/language/en-US/Default.aspx
Why File Through CNS
- Statutory-compliant claim preparation
- Confirmation of filing in the correct Jefferson County
FAQ
How long do I have to file in Jefferson County, OR?
75 days from your last day of labor or materials furnished, or from completion.
Can I still file a lien if I sent my notice late?
Yes, but the lien will only cover work performed in the 8 days before the notice was sent, not earlier work.