MECHANICS LIEN (CONSTRUCTION LIEN) RECORDING IN JEFFERSON COUNTY, OREGON

The Jefferson County Clerk in Madras records construction liens for the high-desert farming region of central Oregon. Here’s the timeline Oregon law requires for getting paid.

Jefferson County Construction Lien Deadlines

  • Notice of Right to Lien: 8 business days from first furnishing on residential jobs, with no direct owner contract.
  • Filing Deadline: 75 days from last furnishing or completion, whichever is earlier (ORS 87.035).
  • Foreclosure Deadline: 120 days from filing.

Jefferson County Clerk’s Office

Why File Through CNS

  • Statutory-compliant claim preparation
  • Confirmation of filing in the correct Jefferson County

FAQ

How long do I have to file in Jefferson County, OR?

75 days from your last day of labor or materials furnished, or from completion.

Can I still file a lien if I sent my notice late?

Yes, but the lien will only cover work performed in the 8 days before the notice was sent, not earlier work.