MECHANICS LIEN RECORDING IN GRANT COUNTY, WASHINGTON
Filing in Grant County, WA? Washington’s 90-day rule applies here just as it does across the state.
Grant County Mechanics Lien Deadlines
- Preliminary Notice: 60 days from first furnishing of labor/materials, if not directly contracted with the owner.
- Filing Deadline: 90 days from last furnishing (RCW 60.04).
- Foreclosure Deadline: 8 months from recording.
Grant County Auditor’s Office
- 35 C St NW, Ephrata, WA 98823
- grantcountywa.gov/auditor/Recording/index.htm
Why File Through CNS
- Legal descriptions are prepared correctly the first time
- Recording and owner service handled end-to-end
FAQ
How long do I have to file a mechanics lien in Grant County, WA?
90 days from the last day you provided labor, materials or equipment.
Does the Auditor’s Office help me fill out the lien form?
No, by law they can only record what’s submitted. CNS prepares the claim for you.
