MECHANICS LIEN RECORDING IN DOUGLAS COUNTY, WASHINGTON

Mechanics lien recording for this apple-growing stretch along the Columbia River in north-central Washington runs through the Douglas County Auditor’s Office in Waterville. Here’s the exact timeline for jobs in the area:

Douglas County Mechanics Lien Deadlines

  • Preliminary Notice: 60 days from first work, if no direct contract with the owner.
  • Filing Deadline: 90 days from your last day of work (RCW 60.04.091) — a claim filed on day 91 is void.
  • Foreclosure Deadline: 8 months from recording.

Douglas County Auditor’s Office

Why File Through CNS

  • We verify you’re filing in the correct Douglas County (WA, OR or NV)
  • We confirm property descriptions
  • We serve the owner within the required 14-day window after recording

FAQ

How long do I have to file a mechanics lien in Douglas County, WA?

90 days from the last day you supplied labor, materials or equipment to the project (RCW 60.04.091).

Where do I record my lien in Douglas County, WA?

With the Douglas County Auditor’s Office in Waterville, the county seat.