MECHANICS LIEN (CONSTRUCTION LIEN) RECORDING IN COLUMBIA COUNTY, OREGON
Based in St. Helens on the Columbia River, the Columbia County Clerk’s Office records construction liens for this northwest Oregon county. Here’s the exact timeline for local jobs.
Columbia County Construction Lien Deadlines
- Notice of Right to Lien: 8 business days from first furnishing, on residential jobs without a direct owner contract.
- Filing Deadline: 75 days from last furnishing or completion, whichever is earlier (ORS 87.035).
- Foreclosure Deadline: 120 days from filing.
Columbia County Clerk’s Office
- 230 Strand St, St Helens, OR 97051
- co.columbia.or.us/departments/county-clerk-main
Why File Through CNS
- We prepare claims that meet Oregon’s exact statutory form
- We ensure you’re filing under the correct Columbia County (OR vs. WA)
FAQ
How long do I have to file in Columbia County, OR?
75 days from your last day of labor or materials furnished, or from completion — whichever is earlier.
Does the 8-day notice need to go out by certified mail?
Oregon’s Notice of Right to Lien should be delivered in a way you can document, and certified mail is generally the safest, standard method.