MECHANICS LIEN RECORDING IN CLARK COUNTY, NEVADA
Filing a mechanics lien in Clark County, NV (Las Vegas metro)? Nevada’s deadline shrinks fast if a Notice of Completion gets recorded.
Clark County Mechanics Lien Deadlines
- Notice of Right to Lien: Must be sent within 31 days of first providing labor or materials
- Notice of Intent to Lien: 15 days before recording, required on residential jobs.
- Filing Deadline: 90 days from last work/materials/completion — or just 40 days if a Notice of Completion is recorded (NRS 108.226).
- Foreclosure Deadline: 6 months from recording.
Clark County Recorder’s Office
- 500 S Grand Central Pkwy 2nd Floor, Las Vegas, NV 89106
- 3211 N Tenaya Wy Suite 118, Las Vegas, NV 89129
- clarkcountynv.gov/recorder/Pages/default.aspx
Why File Through CNS
- We can monitor for a recorded Notice of Completion that shortens your filing window (additional service)
- Statutory claim preparation under NRS 108.226
- We send email reminders for important foreclosure deadlines
FAQ
How long do I have to file a mechanics lien in Clark County, NV?
90 days from your last day providing labor or materials, or completion of work (whichever is later) — but only 40 days if the owner has recorded a Notice of Completion.
What’s a Notice of Intent to Lien?
A required 15-day notice before recording a lien on residential property in Nevada.