MECHANICS LIEN RECORDING IN CLARK COUNTY, WASHINGTON

Filing a mechanics lien in Clark County, WA? The deadline is 90 days — here’s the full timeline.

Clark County Mechanics Lien Deadlines

  • Preliminary Notice: Required within 60 days of first work if you weren’t under direct contract with the owner.
  • Filing Deadline: Record within 90 days of your last day of work (RCW 60.04.091) — courts enforce this to the day.
  • Foreclosure Deadline: You have 8 months from recording to file a foreclosure lawsuit.

Clark County Auditor’s Office

Why File Through CNS

  • Accurate legal descriptions and ownership verification
  • Proper service on the owner within 14 days of recording

FAQ

How long do I have to file a mechanics lien in Clark County, WA?

90 days from your last day supplying labor or materials to the project.

What happens if I miss the 90-day deadline?

Your lien rights are permanently lost; Washington courts don’t grant extensions.