MECHANICS LIEN RECORDING IN BENTON COUNTY, WASHINGTON
Need to file a mechanics lien in Benton County, WA? Washington’s lien statute gives you a strict, non-negotiable window. Here’s exactly what applies.
Benton County Deadlines
- Preliminary Notice: Deliver notice within 60 days of first starting work if you didn’t contract directly with the owner (subcontractors and suppliers on new residential construction have just 10 days).
- Filing Deadline: Record your claim of lien within 90 days of your last day furnishing labor or materials (RCW 60.04.091).
- Foreclosure Deadline: File suit within 8 months of recording if the lien remains unpaid.
Benton County Auditor’s Office
- 620 Market St, Prosser, WA 99336
- 5600 W Canal Dr, Kennewick, WA 99336
- 101 Wellsian Wy Ste E, Richland, WA 99352
- bentonauditor.com/Document-Recording
Why File Through CNS
- We handle recording and service on the owner within the required 14 days
- We remind you after the lien is filed to take the necessary enforcement steps
FAQ
How long do I have to file a mechanics lien in Benton County, WA?
You have 90 days from the last date you supplied labor, materials or equipment to record your claim of lien with the Benton County Auditor.
Do I need to send a preliminary notice in Washington?
Yes, if you didn’t contract directly with the property owner, it must be delivered within 60 days of first furnishing labor or materials — or within 10 days if working on residential new construction.