MECHANICS LIEN (CONSTRUCTION LIEN) RECORDING IN BENTON COUNTY, OREGON

Filing a construction lien in Benton County, OR? Oregon’s deadline is one of the shortest in the country at just 75 days.

Benton County Construction Lien Deadlines

  • Notice of Right to Lien: 8 business days from the first furnishing of labor/materials on residential jobs without a direct owner contract.
  • Filing Deadline: 75 days from last furnishing or project completion, whichever is earlier (ORS 87.035).
  • Foreclosure Deadline: 120 days from filing to bring suit.

Benton County Clerk’s Office

Why File Through CNS

  • We ensure legal descriptions are prepared to ORS 87.035 requirements
  • We record your lien with the county clerks office so you don’t have to
  • We remind you after the lien is filed to take the necessary enforcement steps

FAQ

How long do I have to file a construction lien in Benton County, OR?

75 days from your last day of work or from project completion, whichever comes first.

Do I need to send a notice before filing in Oregon?

Yes, on residential jobs without a direct owner contract, a Notice of Right to Lien is due within 8 business days of starting work.